2010 Schedule of Summer Work
Bond Work
Spring Road Summer/fall 2010
Broadway Summer/fall 2010
Town Wide Paving
Spring Road (Upham Road to Town Line) Fall 2010
Juniper Drive Fall 2010
2010 Crack Sealing
Old Coach Lane 2,698 X 21feet
Limbo Lane 1,246 X 26 feet
Beaver Brook Circle 2,207 X 19 feet
Northfield (Boston Post to Stop sign) 1,500 X 24 feet
Martingale Road (Boston Post to Melendy Hollow) 1,400 X 24 feet
Cricket Hill Drive from (Boston Post Rd to #7) 1,650 X 24 feet
Monticello Drive 2,150 X 24 feet
Fairway Drive 3,987 X 20 feet
River Road 2,213 X 20 feet
Meadow Lane 1,652 X 24 feet
South Fire Station Parking lot
Total 20,703 feet (3.92 mi)
Surface Treatment Chip Seal
Late August 2010
Road Name Miles feet width Sq Yds
Beaver Brook Circle 0.418 2,207 19 4,660
Brookwood Drive 0.179 946 20 2,102
Buckridge Drive 1.069 5,644 21 13,170
Cobbler Lane 0.179 945 23 2,415
Crocket Lane 0.171 903 24 2,408
Flanders Road 0.093 491.04 20 1,091.2
Limbo Lane 0.236 1,246 26 3,600
Old Coach Ln. 0.511 2,698 21 6,295
Shadow Ln 0.379 2,001 19 4,224
Sunset Ave 0.096 520 18 1,040
Thatcher Drive 0.26 1,372 24 3,659
July/ August Drainage Work
Juniper Drive Replace 70 feet culvert pipe
Amherst Street Replace 800 feet culvert pipe
4 catch basins
Spring Road (town work) Replace 60 feet culvert pipe
2011 Proposed Bond Work
Sections of
Pulpit Run Thistle Road Parkhurst Drive
Pine Road Old Manchester Road Hubbard Road
Sprague Road Mack Hill Road Boston Post Road
Mont Vernon Road Christian Hill Road Dodge Road